Projects>Energy

Electrical Power HVElectrical Distribution



Client: SEC/SOA
Project name: Dahran Al Janoub & Al Khaniq S/S
Project Description Reinforcement including - 2 transformers, 50/67 mva, 132/13.8 kv, 12 feeders bay 132 kv, 14 feedersbay 13.8 kv, 4 chargers, 2 batteries, relay and control panels, civil.
Contact: Abdullah A. Al Ghamdi
Telephone: 07-2271528
Location: Najran Area
Start Date: 27/05/2006
Completion Date: 26/07/2008
Construction Value (SR):
Client: SEC/SOA
Project name: KKAB S/S
Project Description Reinforcement including - 3 transformers, 50/67 mva, 132/13.8 kv, 3 neutral earthing resistance, 1 transformers bay 132 kv, 37 feeders bay 13.8 kv, 2 chargers, 1 battery, relay and control panels, civil.
Contact: Abdullah A. Al Ghamdi
Telephone: 07-2271528
Location: Khamis Mishait
Start Date: 15/04/2006
Completion Date: 15/03/2008
Construction Value (SR):
Client: SEC/SOA
Project name: Baha East S/S
Project Description Reinforcement including 3 feeders bay 132 kv, 1 capacitor bank, relay and control panels, civil.
Contact: Abdulla Al Ghamdi
Telephone: 07-2319153
Location: Baha Area
Start Date: 27/05/2006
Completion Date: 26/05/2008
Construction Value (SR):
Client: SEC/SOA
Project name: Baish S/S
Project Description Reinforcement including 2 transformers, 133/106/80 mva, 132/33/13.8 kv, 2 earthing transformers, 19 feeders bay 13.8 kv, 2 chargers, 1 battery, relay and control panels, civil
Contact: Abdullah A. Al Ghamdi
Telephone: 07-2271528
Location: Jizan Area
Start Date: 15/04/2006
Completion Date: 14/05/2008
Construction Value (SR):
Client: SEC/SOA
Project name: Oukdud S/S
Project Description Reinforcement including 2 transformers, 50/67 mva, 132/13.8 kv, 2 neutral earthing resistance, 22 feeders bay 13.8 kv, 2 chargers, 1 battery, relay and control panels, civil
Contact: Abdullah A. Al Ghamdi
Telephone: 07-2271528
Location: Najran area
Start Date: 15/04/2006
Completion Date: 14/05/2008
Construction Value (SR):
Client: SEC/SOA
Project name: Various Reinforcement S/S
Project Description Reinforcement including 2 feeders bay 33kv at sabya s/s, 3 feeders bay 33kv at abuarish s/s, 2 feeders bay 13.8 kv at Jizan town s/s.3 feedersbay 13.8kv at bisha town s/s. 6 feeders bay 13.8 kv at abha east s/s, relay and control panels, civil
Contact: Abdullah A. Al Ghamdi
Telephone: 07-2271528
Location: Southern Region
Start Date: 15/04/2006
Completion Date: 14/05/2008
Construction Value (SR):
Client: SEC/SOA
Project name: Jizan Town S/S
Project Description Reinforcement including 2 transformers 133 mva, 132/33/13.8 kv, 2 earthing transformers, 16 feeders bay 13.8 kv, 1 battery, 2 chargers, relay and control panels, scada, civil
Contact: Abdulla Al Ghamdi
Telephone: 07-2271528
Location: Jizan Area
Start Date: 16/12/2006
Completion Date: 16/01/2009
Construction Value (SR):
Client: SEC/SOA
Project name: Sabya S/S
Project Description Reinforcement including - 2 transformers 133mva, 132/33/13.8 kv, 2 earthing transformers, 16 feeders bay 13.8 kv, 1 battery, 2 chargers, relay and control panels, scada, civil.
Contact: Abdullah A. Al Ghamdi
Telephone: 07-2271528
Location: Jizan Area
Start Date: 16/12/2006
Completion Date: 16/01/2009
Construction Value (SR):
Client: SEC-SOA
Project name: Baljurashi North S/S
Project Description construction including - 2 transformers50/60 mva, 132/13.8 kv , 2 aux transformers, 4 feeders bay 132 kv, 1 capacitor bank 20 feeders bay 13.8 kv, 1 battery, 2 chargers, relay and control panels, scada, civil
Contact: Abdullah A. Al Ghamdi
Telephone: 07-2271528
Location: BALJURASHI
Start Date: 16/12/2006
Completion Date: 15/09/2008
Construction Value (SR):
Client: SEC-SOA
Project name: Al Haramain Road S/S
Project Description construction including - 8 GIS bay 132 kv, 3 transformers 60 mva, 132/13.8 kv, 2 aux transformers, 34 feeders bay 13.8 kv, 2 Chargers, 1 battery relay and control panels,ac/dc panels, scada, civil
Contact: MAGID ALMALIKI
Telephone: 555704881
Location: Jeddah
Start Date: 13/12/2006
Completion Date: 13/09/2008
Construction Value (SR):
Client: SEC-SOA
Project name: alqamariya s/s
Project Description construction including - 8 GIS bay 132 kv, 3 transformers 60 mva, 132/13.8 kv, 2 aux transformers, 34 feeders bay 13.8 kv, 2 Chargers, 1 battery relay and control panels, ac/dc panels, scada, civil
Contact: MAGID ALMALIKI
Telephone: 555704881
Location: Taif
Start Date: 13/12/2006
Completion Date: 13/09/2008
Construction Value (SR):
Client: SEC-WN
Project name: tabouk 1& 7
Project Description Reinforcement including - 12 feeders 13.8 kv at tabouk-1, 10 feeders 13.8 kv at tabouk-7 including relay and control panels, scada, civil
Contact: AKIL ALATAS
Telephone: 04 - 8615511 EXT 230
Location: Tabouk
Start Date: 13/12/2006
Completion Date: 13/08/2008
Construction Value (SR):
Client: SEC-WOA
Project name: AL-AMAL S/S
Project Description New AL-AMAL 110/13.8 KV Substation ( Jeddah Substation and Transmission line Portion )
Contact: Ali bukhshan
Telephone: 0555525820
Location: AL-AMAL
Start Date: 18/02/2008
Completion Date: 17/11/2009
Construction Value (SR):
Client: SEC-WOA
Project name: NUZLA
Project Description New Nuzla -2 100/13.8 kv Substation in Jeddah AREA
Contact: Ali bukhshan
Telephone: 0555525841
Location: AL- NUZLA -2
Start Date: 18/02/2008
Completion Date: 17/11/2009
Construction Value (SR):
Client: SEC-WOA
Project name: ICY 4
Project Description New ICY 4 110/13.8 KV Substation (Jeddah ) ( Substation and Transmission Line Portion )
Contact: Aiman Yamani
Telephone: 0555530783
Location: ICY 4
Start Date: 18/02/2008
Completion Date: 17/11/2009
Construction Value (SR):
Client: SEC-WOA
Project name: Al-Shoran
Project Description Construction of new 110/13.8 kv shoran S/S at Madinah
Contact: Ahmed AL-Gohany
Telephone: 05-56137468
Location: Al-Shoran
Start Date: 29/03/2008
Completion Date: 01/07/2010
Construction Value (SR):
Client: Saudi Electricity Company Southern Operating Area (SEC-SOA)
Project name: Al-Birk S/S
Project Description Replenishment of 132/33 KV S/S
Contact: Plani Swami
Telephone: 05-62345806
Location: Al-Birk
Start Date: 19/08/2008
Completion Date: 18/12/2009
Construction Value (SR):
Client: Saudi Organization for Industrail Estates & Technology Zones (SOIETZ)
Project name: 132/13.8 KV substation & 132KV D/C OHTL at Jizan industrial Area
Project Description (i) Construction of new 132/13.8kV S/S Including- GIS, Transformers, 13.8kV switchgear, Relay/Control, SCADA, Fire fieghting, HVAC, Cables and civil works (ii) 8.5km, 132kV D/C OHTL From Kudmi 380/132kV S/S To Jizan Industrial 132/13.8kV S/S
Contact: Abdullah Al Ghamdi
Telephone: 07- 2271528 07-2271111
Location: Jizan
Start Date: 21/09/1429 H
Completion Date: 21/05/1431 H
Construction Value (SR):
Client: Saudi Organization for Industrail Estates & Technology Zones (SOIETZ)
Project name: 110/13.8 KV ICY-5 substation & 110 KV OHTL at Jeddah industrial Area
Project Description (i) Construction of new 110/13.8kV ICY-5 S/S Including- GIS, Transformers, 13.8kV switchgear, Relay/Control, SCADA, Fire fieghting, HVAC, Cables and civil works (ii) 80km, 110kV OHTL between 380/110kV Shoaiba P.P & New 110/13.8kV ICY-5 S/S
Contact: Mohd. Jamil mannan
Telephone: 02 6537340
Location: Jeddah
Start Date: 12/10/1429H
Completion Date: 12/06/1431H
Construction Value (SR):
Client: Saudi Electricity Company West Operating Area (SEC-WOA)
Project name: Construction of New 132 KV Tabuk (5B) S/S
Project Description Construction included 20 GIS 132kV bays along with control and protection scheme , SCADA, AC/DC, Cables and civil works
Contact: Engr.Nabil G Khushaim
Telephone: 04 8615511
Location: Tabuk
Start Date: 05/11/2008
Completion Date: 05/12/2010
Construction Value (SR):
Client: Ministry of Higher Education
Project name: Hail University
Project Description Construction of New 132/13.8 KV Hail S/S
Contact: Mohamed Al Hoglain
Telephone: 0555286988
Location: Hail Area
Start Date: 24/03/2009
Completion Date: 24/05/2011
Construction Value (SR):
Client: SEC
Project name: Addition of Nine (9) 13.8KV U/G Feeder Panels in S/S Nos. 7904.7905.7906 In Hail Area
Project Description Supply, Installation, Testing and Energizing of Nine (9)13.8kV ,400A U/G Fedder Panels in S/S Nos. 7904.7905.7906 In Hail Area
Contact: Hussain AL Sagoorr
Telephone: 050445669
Location: Hail Area
Start Date: 25/05/2009
Completion Date: 25/08/2010
Construction Value (SR):
Client: Saline Water Conversion Corporation (SWCC)
Project name: Power Supply to Pumping Stations of Shuqaiq Phase (2) Water Transmission System, Package – II
Project Description 1-Construction of three new GIS 132/13.8 kV S/S at Pumping Stations PSA2, PSA3 and PSA4 2-Construction of three new 33/13.8kV Substations at Pumping Stations PSDJ, PSR1 & PSR2. 3-Extension of two 33kV Switchgear Panels at existing two Substations
Contact: Hasan Fakeh
Telephone: 05 55768410
Location: Abha, Jizan, Al-Birk, Samitah
Start Date: 6/12/2009
Completion Date: 6/6/2011
Construction Value (SR):
Client: King Khaled University
Project name: N/A
Project Description - Construction of new 132/13.8kV S/S - 13.8kV Switchgear building inside King Khaled University - 132kV DC OHTL to feed King Khaled University, Abha area.
Contact: N/A
Telephone: N/A
Location: Abha
Start Date: 16/8/2009
Completion Date: 16/8/2011
Construction Value (SR):
Client: Saudi Telecom Company (STC)
Project name: Out side network OSP
Project Description Supply, Installation, testing & commissioning for the material and equipment required for Connecting power to out side network (NGN) all over the kingdom
Contact: Mr. Abd ulmoti A. Dahlawi
Telephone: 0504012388
Location: Entire Kingdom of Saudi Arabia
Start Date: 27/3/1430
Completion Date: 26/9/1431
Construction Value (SR):
Client: Saudi Telecom Company (STC)
Project name: Rehabilitation of technical Building
Project Description Supply, Installation, testing & commissioning for the material and equipment required for Connecting power to GSM-STC sites located at Roads & Villages- all over the Kingdom through either commercial power or Generators.
Contact: Mr. Rajeh
Telephone: 0504720729
Location: Entire Kingdom of Saudi Arabia
Start Date: 26/05/2009
Completion Date: 25/11/2010
Construction Value (SR):
Client: Saudi Telecom Company (STC)
Project name: Power connection to GSM Sites for AlJawal (2009 projects (C-9)
Project Description Supply, Installation, testing & commissioning for the material and equipment required for Connecting power to GSM-STC sites located at Roads & Villages- all over the Kingdom through either commercial power or Generators.
Contact: Mr. Ahmad AlSaraa
Telephone: 0555426098
Location: Entire Kingdom of Saudi Arabia
Start Date: 27/3/1430
Completion Date: 26/9/1431
Construction Value (SR):
Client: SEC/SOA
Project name: Maintenanace of Distribution Network Medium Voltage up to 33KV & Low Voltage
Project Description Maintain all Activities of maintenance of Diistribution network medium voltage up to 33KV & low voltage in accordance with the scope of work.
Contact: Mr. Mohammed Mansour
Telephone: 0556203330
Location: Southen Operating Areas
Start Date: 8/10/2007
Completion Date: 7/10/2010
Construction Value (SR):
Client: SEC/SOA
Project name: The Unified Contract for Overhead &Under ground Distribution Networks up to 35KV In Jizan Area
Project Description Install, remove, replace and modify overhead distribution facilities for operating voltage up to and including 35KV in accordance
Contact: Mr. Mohammed Mansour
Telephone: 0556203330
Location: Southen Operating Areas Jazan
Start Date: 09/02/2008
Completion Date: 09/02/2011
Construction Value (SR):
Client: SEC/SOA
Project name: The Unified Contract for Overhead &Under ground Distribution Networks up to 35KV In Assir Area
Project Description Install, remove, replace and modify overhead distribution facilities for operating voltage up to and including 35KV in accordance
Contact: Mr.Mohamed Mansour
Telephone: 0556203330
Location: Southen Operating Areas Assir
Start Date: 09/02/2008
Completion Date: 09/02/2011
Construction Value (SR):
Client: Zain
Project name: Power Connection to Zain-Telecom sites
Project Description Supply, install, test & commission power connection throughgenerator to Zain Telecom sites, in the Kingdom of Saudi Arabia.
Contact: Mr.Khalil AlHarith
Telephone:
Location: Entire Kindom of Saudi Arabia
Start Date: 01/04/2009
Completion Date: 01/04/2010
Construction Value (SR):
Client: Etihad Etsalat Company (MOBILY)
Project name: Supply and installation of Skid mtd. Generator
Project Description Supply, install, test & commission power connection throughgenerator to BSC/Telecom Building, on demand, at the designated site in the Kingdom of Saudi Arabia.
Contact: Mr. Saad Al Shagrawy
Telephone: 0569282789
Location: Entire Kindom of Saudi Arabia
Start Date: 10/27/2009
Completion Date: 11/01/2010
Construction Value (SR):
Client: Etihad Etsalat Company (MOBILY)
Project name: Power Connection to AlDANA Site
Project Description Supply, install, test & commission power connection to AlDanah site
Contact: Mr. Saad Al Shagrawy
Telephone: 0569282788
Location: Riyadh
Start Date: 01/07/2009
Completion Date: 01/11/2009
Construction Value (SR):
Client: Etihad Etsalat Company (MOBILY)
Project name: Power Connection to BSC/Telecom Building
Project Description Supply, install, test & commission power connection to BSC/Telecom Building, on demand, at the designated site in th e Kingdom of Saudi Arabia.
Contact: Mr. Saad Al Shagrawy
Telephone: 0569282787
Location: Entire Kindom of Saudi Arabia
Start Date: 05/06/2008
Completion Date: 05/06/2010
Construction Value (SR):
Client: NATIONAL GUARD HEALTH AFFAIRS KING ABDULAZIZ MEDICAL CITY
Project name: SCECOIZATION of Medical City
Project Description Connecting SEC power to MC, by laying the necessarycables and transformers erection with all required accessories, removing the old equipment and install new ones to be compatible with SEC power, finish all the civil and electromechanical work to accomodate the new system
Contact: Mr. Sami AlSaleh
Telephone: 0505778915
Location: Riyadh
Start Date: 01/11/2009
Completion Date: 01/05/2010
Construction Value (SR):
Client: MINISTRY OF DEFENCE AND AVIATION \ AIR DEFENCE
Project name: SEC POWER SUPPLY FOR ARFAA SITE AT TAIF
Project Description Connecting SEC power to Air defence site in Arfaa (Taif), by supply and installation of the overhaead line, underground cables and transformers with all required equipment andaccessories,preparing all the civil and electromechanical work to accomodate the new system
Contact: Mr. Mohammed Ghaith
Telephone: 0507520031
Location: Taif
Start Date: 17/10/2009
Completion Date: 16/10/2010
Construction Value (SR):
Client: SEC/SOA
Project name: CONSTRUCTION SUPPLY INSTALLATION FOR 33 KV OVERHEAD IN SOME VILLAGE IN JIZAN VILLAGE 2
Project Description Delivery and Installation of the electric materials and equipment (Poles, Transformers, cables and conductors)to supply the SEC power to the villages of JIZAN VILLAGE 2
Contact: Mr. Ali Misfer
Telephone: 0555757097
Location: Jizan - South region
Start Date: 28/09/2009
Completion Date: 28/09/2011
Construction Value (SR):
Client: SEC/SOA
Project name: CONSTRUCTION SUPPLY INSTALLATION FOR 33 KV OVERHEAD IN SOME VILLAGE IN ZAHRAN AL GANOUB
Project Description Delivery and Installation of the electric materials and equipment (Poles, Transformers, cables and conductors) to supply the SEC power to the villages of ZAHRAN AL GANOUB
Contact: Mr. Ali Misfer
Telephone: 0555757097
Location: ASSIR- South region
Start Date: 28/9/2009
Completion Date: 28/9/2011
Construction Value (SR):
Client: SEC/SOA
Project name: CONSTRUCTION SUPPLY INSTALLATION FOR 33 KV OVERHEAD IN TAREEB VILLAGE
Project Description Delivery and Installation of the electric materials and equipment (Poles, Transformers, cables and conductors) to supply the SEC power to the villages of Tareeb
Contact: Mr. Ali Misfer
Telephone: 0555757097
Location: ASSIR- South region
Start Date: 28/9/2009
Completion Date: 28/9/2011
Construction Value (SR):
Client: SEC (WOA)
Project name: Construction of 110/13.8KV AlANDALOS-2 @ Jeddah
Project Description Design, Engineer, Procure, Supply and Deliver All Materials/Equipment to the Work Site Construction, Install, test and commission and put into service in accordance for construction of 110/13.8 AlANDALOS-2 @ Jeddah
Contact: Saleh M. Al-Onaizan
Telephone: NA
Location: Jeddah
Start Date: 22/3/2010
Completion Date: 20/5/2012
Construction Value (SR):
Client: SEC (WOA)
Project name: Construction of 110/13.8KV BANI AL NAJJAR @ MADINAH S/S
Project Description Design, Engineer, Procure, Supply and Deliver All Materials/Equipment to the Work Site Construction, Install, test and commission and put into service in accordance for construction of 110/13.8 BANI AL NAJJAR @ MADINAH S/S
Contact: Saleh M. Al-Onaizan
Telephone: NA
Location: Madina
Start Date: 22/3/2010
Completion Date: 20/5/2012
Construction Value (SR):